|
On June 12, 2001 PIC published a new
draft on isolator technology. Like all PIC documents dealing with this
subject, this document is also not binding for the industry but addresses
inspectors belonging to the supervisory authority. However, the industry
can see from these documents what areas the supervisory authorities will
concentrate on in future inspections of isolator systems.
Historical background: A first attempt to
define requirements for isolator technology was made by PIC in 1997 with
the publication of the document PS/W 3/97 "Inspection of Isolator
Technology". This was soon followed at the end of 1999 by a new draft
"Revised draft submitted to Committee PE 004-1" but which was
withdrawn again in February 2000 owing to considerable objections by the
industry.
In April 2001 PIC embarked on a new
attempt, which was published in June 2001as PE 004-1 Draft 3 for
commenting by the industry. The deadline for comments expires at the end
of September 2001.
Fundamental differences between the
various versions:
While the 1999 draft described many
aspects of isolator technology in great detail the structure of the new
draft was considerably simplified. On only 6 pages (in the 1999 draft 20
pages) the fundamental requirements were briefly described.
- Document history
- Introduction
- Purpose
- Scope
- Definitions / Glossary
- Principles related to the selection
and use of gassed isolators
- Detailed points to be considered for
the implementation of the principles for gassed isolators
- Revision history
Details on Item 7, particularly on
decontamination and the prevention of recontamination are specified in an
approximately 13-page appendix dealing especially with the following
points:
- Principles related to the selection
and use of gassed isolators
- Training
- Materials
- Sporicidal treatment (very detailed)
- The prevention of recontamination
(very detailed)
As an example the chapter on sporicidal
treatment is to be shown with some of its own headlines in somewhat
greater detail.
Requirements
- The substance for the gas
sterilization is to be sporicidal
- The correct identity and composition
of the substance used for gaseous sterilization is to be ensured
- It is not to be assumed that all gas
generators are the same
- Staff should understand how the gas
generators work
- Critical parameters are to be
identified and recorded throughout the entire process
- Measuring instruments are to be
calibrated
- It is to be ensured that all
critical parameters achieve the specifications defined during
validation
- All inlet and outlet filters are to
come into contact with the gas during gassing. Air for rinsing the
gas should be sterile filtered
- The isolator is to be cleaned before
gassing
- The cooling zone of the integrated
sterilization tunnel is to be sterilizable
- Before the isolator is released for
production it is to be checked that the gassing cycle is adhered to
- Process parameters should be
recorded
- The design, the development and the
validation of the gassing process should include all relevant
aspects, e.g. methods of gas distribution, lethality rates,
calibration, protocols, etc.
- The requirements for the
requalification and the interpretation of the results are to be
defined prospectively
The draft can be downloaded at http://www.picscheme.org/pubs/PICSIsolatortechnologyPE004-1.pdf
Author: Dr.
Andreas Mangel, CONCEPT HEIDELBERG
|